Cheltenham Badlands Parking Lot Update

Here are the following updates I have received over the past 2 months in regards to the Badlands Parking lot project. They have done a great job at keeping us up-to-date to everything that has been completed and projected. Please contact me if you have any further questions.

MAY 24

Update #5 

Work Progress During Last Two Weeks:

·        Completed patterned concrete barrier wall

·        Completed placement of granular sub-base material within the proposed lot

·        Commenced placement of topsoil and erosion control blanket behind patterned concrete barrier wall

 Work to be Performed in the Next Two Weeks:

·        Commence placement of concrete curbs within the proposed lot

·        Commence placement of toe wall

·        Commence placement of sidewalk

·        Commence planting trees and shrubs

 

 

 

MAY 10 

Update #4 

 Work Progress During Last Two Weeks:

•             Completed excavation (cutting/filling) operations for the parking lot

•             Completed placement of granular material for the walkway/walls and road

•             Commenced concrete works: pattern concrete barrier wall

 Work to be Performed in the Next Two Weeks:

•             Continue concrete works: walls, sidewalk, curbs

•             Commence granular placement within the parking lot

We have been battling wet weather and have lost approximately 2 weeks due to it.  Our Contractor is still committed to complete the project on time, if not ahead of schedule.

  

cid:0fde9df3-5b4d-45e7-90b1-746621ed7209@CANPRD01.PROD.OUTLOOK.COM

APRIL 25 

Update #3

 

Work Progress During Last Two Weeks:

•             Completed highway fence removal of in front of proposed parking lot location

•             Completed clearing and grubbing/tree removal operations within the lot

•             Completed stripping of top soil within the proposed lot

•             Completed replacement of storm sewer roadway culverts for Badlands project

•             Installed 2 Double Catchbasin structures along the South side of Olde Base Line Road

•             Commence excavation (cutting/filling) operations

•             Removed asphalt along the south side of Olde Base Line Road for pedestrian walkway

Work to be Performed in the Next Two Weeks:

•             Continue excavation (cutting/filling) operations

•             Commence placement of granular material within the lot and for the walkway

•             Commence concrete works: walls, curbs, islands, walkway

 

cid:f9f3bf00-6909-4936-9376-f7e5dd7efb98@CANPRD01.PROD.OUTLOOK.COM

 

APRIL 12 

Update #2 on Badlands project:

Work Progress During Last Two Weeks:

•             Mobilized to site on April 3, 2017

•             Set-up site trailer

•             Installed 4 PVMS, 2 project signs and construction signs

•             Installed silt fence around the perimeter of the proposed parking lot

•             Commenced removal of highway fence in front of proposed parking lot location

•             Commenced clearing and grubbing/tree removal operations within the lot

•             Installed temporary concrete barrier wall along the centre line of Olde Base Line Road, in the vicinity of Badlands

•             Installed temporary traffic signals at East and West Limits of Badlands Parking Lot project

•             Commenced replacement of storm sewer roadway culverts for Badlands project

•             Commenced the removal of guide rail

 

Work to be Performed in the Next Two Weeks:

•             Complete highway fence removal of in front of proposed parking lot location

•             Complete clearing and grubbing/tree removal operations within the lot

•             Complete replacement of storm sewer roadway culverts for Badlands project

•             Commence stripping of top soil within the proposed lot

•             Commence excavation (cutting/filling) operations and placement of granular material within the proposed lot

•             Saw cut/grind/remove asphalt along the south side of Olde Base Line Road for pedestrian walkway

•             Commence excavation and granular placement for pedestrian walkway

•             Commence concrete works: walls, curbs within parking lot and on Creditview Road

•             Excavation and granular placement at Creditview Road

  

cid:image001.jpg@01D2B431.D9465CB0

 

·        Construction has commenced as of this morning, April 3, 2017

o   We’ve delivered residential notices directly to every doorstep for all residents in the vicinity of the site

o   We’ve installed 2 project sign boards and 4 electronic message boards far in advance of the work area.  All electronic boards are fully functioning

o   Survey for the proposed parking lot is being carried out

o   Fence at the proposed parking lot area is being removed

o   Silt fence around the proposed parking lot area is being installed

o   Tree removal will commence tomorrow

 

·        In the next two weeks, the following activities will be happening at the site:

o   Closure of the eastbound lane (south side of the road): installation of temporary concrete barrier wall along the centre of the road and temporary signals installation

o   Culvert replacements

o   Tree and top soil removal

o   Excavation of existing material and placement of new granular

o   Concrete works

o   Creditview and Olde Base Line Intersection works

 

·        Monday, April 10, 2017 (weather permitting)

o   Olde Base Line Road will be temporarily closed in all directions between Creditview and Chinguacousy, from 07:00AM to 5:00PM, to complete culvert replacements at Badlands, temporary concrete barrier and temporary signal installation

o   OPP pay duty will be on site to re-direct the traffic around the area

o   Local residents within that area will have access to enter/exit

o   Brampton Fire (looking after Caledon) has been notified as of this morning.  Emergency vehicles and school busses will have access at all times

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s