Cheltenham Badlands Update

Work Progress During Last Two Weeks:

·        Completed planting trees and shrubs/top soil and mulch within the proposed parking lot

·        Completed placement of Low-Impact-Development (LID) features within the proposed parking lot

·        Completed placement of concrete curbs at Creditview and Olde Base line Intersection

·        Switched traffic to the South side of the roadway – works continued on the North side

·        Completed regrading of the North slope across from the Badlands feature

Work to be Performed in the Next Two Weeks:

·        Complete placement of concrete curbs along the North side

·        Complete patterned colour concrete splash pad

·        Continue ditching, placement of seed and mulch

·        Remove temporary concrete barrier

·        Commence asphalt milling on Olde Base Line Road

·        Commence placement of base asphalt on Olde Base Line Road

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s